SAI DESIGNS PA'S FIRST POST-TENSIONED BRIDGE
PIER CAP WITH ALGOR FEA
| Curved bridge is shown here under construction. Preparations
are underway for post-tensioning of the pier cap. The bridge
is located near Pittsburgh, Pennsylvania. |
The city of Pittsburgh is well known in the bridge building industry.
Small wonder with three rivers running through the center of the
city. That is why the International Bridge Conference and Exhibition
is held in Pittsburgh every year.
This year's conference will include a paper by Ahmad Ahmadi,
Ph.D., P.E., Lead Engineer, Research and Development for SAI Consulting
Engineers, a leading Pittsburgh-based engineering firm. The subject
of Dr. Ahmadi's presentation is his recent design of a curved
bridge which utilizes an integral post-tensioned concrete pier
cap. This is the first such pier cap design in the Commonwealth
of Pennsylvania.
Complex Curved Design
Curved bridges offer some tremendous challenges to engineers.
In this case, the inclusion of integral pier caps added to the
challenge. It was because of this complexity, and the requirement
for a safe design, that Dr. Ahmadi chose to perform finite element
analysis using Algor software.
"To have a safe design, forces such as shear, axial, moment and
torsion should be computed accurately," says Dr. Ahmadi. "Therefore,
the structure should be analyzed in 3-D and influence surfaces
prepared for each element of the superstructure and substructure.
Later, these surfaces must be loaded with moveable live loads
to simulate traffic conditions.
"The design of the bridge was dictated by geometric constraints
which needed to be met at the bridge site," he continues. "The
bridge roadway had a predefined elevation, the required span lengths
of the structure dictated the girder depth and the roadway passing
under the structure had a required vertical clearance."
| Ahmad Ahmadi, Ph.D. created finite element models to
optimize the design of a curved bridge which incorporated
a post-tensioned pier cap. |
Standard Design Would Not Work
"Standard pier designs place the top of the pier cap below the
girder's bottom flanges. This would have placed the underside
of the pier arms below the required clearance elevation. The decision
to cast the girders into the pier cap averted the unreasonable
and expensive alternative of a sharply skewed pier. A sharp pier
skew creates a longer pier which adds to the complexity of the
superstructure behavior under loadings, especially seismic loads."
Post-Tensioning Necessary
"Since casting the girders into the pier cap resulted in it being
segmented from a structural perspective, post-tensioning was necessary.
This requirement meant that torsion, moment, shear and axial forces
had to be calculated in the pier cap in order to permit a reliable
design of the post-tensioning system."
Two Models Created
To perform the analyses, Dr. Ahmadi constructed two Algor FEA
models. The first represents the complete structure and utilized
976 beam, 212 truss, 380 brick and 13 boundary elements. The model
contains 1463 nodes.
For accurate modeling of the girders, Dr. Ahmadi used separate
beam elements for the top flange, web and bottom flange. These
elements were centered at different elevations and connected by
stiff elements. This permitted determination of the moments at
a cross section from the axial forces given in the output. According
to Dr. Ahmadi, "This level of analysis produced a more refined
design of the girder than acceptable 2-D methods would, thus saving
on material costs."
To study the behavior of the pier more closely, Dr. Ahmadi constructed
a separate, more detailed model of just the pier. This model contains
514 brick elements, 23 boundary elements and 813 nodes.
| A closer view of the curved bridge FEA model. |
Analysis Results
"The results of the analyses gave reasonable forces which could
be handled by standard materials and averted the problems created
by the geometric constraints," says Dr. Ahmadi. "The pier behavior
was compared with available full-scale laboratory tests on similar
piers and revealed a good correlation."
While specializing in the 3-D analysis and design for bridges,
SAI Consulting Engineers, Inc. has handled such diverse assignments
as the analysis of nuclear containment systems during decommissioning,
thermal analysis of chemical vessels subjected to extreme temperatures
and many other analysis projects. SAI is the only consulting engineering
firm in Pennsylvania to have developed a 3-D analysis and design
package accepted by the Pennsylvania Department of Transportation.
According to Dr. Ahmadi, "Algor software stands out in the numerous
user interfaces available for generating and viewing models. To
generate influence surfaces for each element of the model, more
than 170 load cases were considered. This large amount of data
needed to be manipulated for use by our 3-D live load influence
surface loader. Algor post processors made it easy to accomplish
this task."
|
|
| Series of photos shows additional details of bridge construction
in progress. |
|